How long are permits good for?

Since January 1, 2009, Building Permits issued under non-enforcement circumstances have been issued for a term of 3 years. All work and inspections must be completed within 3 years from the date of issuance.  Any work or inspections pending after 3 years will require an additional finish permit.  The Finish permit project review will be based on codes current at the time of new issuance for work uninspected and unapproved. Fees to finish will also be based on an adjusted amount per the current fee schedule for the amount of work not previously inspected.